entièrement revêtu sur les deux faces
numéro d'article 070430
Bandes de tôle d’étanchéité VB
joint sheet metal, 160 mm wide
length 2.4 m
50 pcs. per crate
incl. 55 fixing clips
water pressure test by MFPA Leipzig
groundwater neutral
Aperçu des informations les plus importantes
St 37, galvanisé
.
Revêtement spécial : Plastique polymère renforcé par un tissu
2,4 m
160 mm
approx. 0,6 mm
approx. 0,15 mm
approx. 0,9 mm
Test report PB 5.1/14-423-3
MFPA Leipzig
yes
Utility class A for the wear classes 1 and
2 in accordance with the WU guideline
No
yes
wooden crate (255 x 30 x 25 cm)
50 strips
55 fixing clips
12 crates per pallet
Joint sheet metal which has been installed during the first construction stage already must not be exposed to free UV weathering for more than 4 weeks until completely cast in concrete. If construction is interrupted for a prolonged period, the joint sheet metal must be especially protected against UV radiation (dark foils etc.) in order to preserve usability.
Test technique d'application jusqu'à 8 bar
Remove the bottom half of the parted protective foil from the special coating.
Place the VB joint sheet metal in the centre of the rising wall on top of the upper reinforcement layer.
Push the mounting brackets with a maximum distance of 70 cm over the sheet metal and fix them to the upper reinforcement layer with binding wire.
The embedment depth in the concrete must be at least 3 cm and must not be more than half the height of the sheet metal.
The VB joint sheet metal must overlap by at least 6 cm in the area of the joint, in the straight sections and also in the corner area.
To do so, the upper protective foil must be turned back in the area subsequently to be joined.
Overlap the VB joint sheet metal by at least 6 cm and press the two ends firmly together.
The joint must be glued over its full height and entire surface to prevent subsequent water permeation.
There must be no contamination on the adhesive surfaces that could interfere with bonding.
Secure the joint with one of the fixing clips provided and fold the protective foil back onto the special coating.
Prepared joints in the straight sections as well as the corner area.
Once the foundation slab has been concreted, and before the wall formwork is closed or the double wall elements have been set up, the remaining protective foil must be removed.
The concreting of the wall base and corresponding preparations must be carried out in accordance with the established technical standards.
Status: 23.03.2022
accessoires
accessoires appropriés
The joint sheet metal/joint tape connector establishes a reliable pressure water-tight connection between PVC joint tapes and coat...
Elément angulaire 90° préfabriqué ...
Elles permettent de sécuriser les joints de chevauchement de couvre-joints métalliques revêtus. ...
Etriers de fixation pour couvre-joints métalliques pour couvre-joints métalliques revêtus et non revêtus à hauteur 160 mm ...
Produits similaires
Vous trouvez ici des produits similaires.
40 unités a 2,5 m Certificat national d'agrément technique général par MFPA Leipzig. ...
larguer 160 mm épaisseur1,8 mm emballé en carton avec 30 étriers de fixation avec 2 goupilles de sécurité Certificat national d&#...
Contactez nous
We are happy to answer your questions