Aperçu des informations les plus importantes
St 37, galvanisé
.
Revêtement spécial : Plastique polymère renforcé par un tissu
160 mm
approx. 0,6 mm
approx. 0,15 mm
approx. 0,75 mm
Test report PB 5.1/14-423-3
MFPA Leipzig
yes
Utility class A for the wear classes 1 and
2 in accordance with the WU guideline
no
yes
Joint sheet metal which has been installed during the first construction stage already must not be exposed to free UV weathering for more than 4 weeks until completely cast in concrete. If construction is interrupted for a prolonged period, the joint sheet metal must be especially protected against UV radiation (dark foils etc.) in order to preserve usability.
carton (40 x 40 x 20 cm)
1 roll
2 fixing clips
36 cartons per pallet
Test technique d'application jusqu'à 8 bar
Remove the bottom half of the parted protective foil from the special coating.
Place the VB joint sheet metal in the centre of the rising wall on top of the upper reinforcement layer.
Push the mounting brackets with a maximum distance of 70 cm over the sheet metal and fix them to the upper reinforcement layer with binding wire.
The embedment depth in the concrete must be at least 3 cm and must not be more than half the height of the sheet metal.
PLEASE NOTE!! The coating of the joint sheet metal VB1 must face the waterlogged side!
The VB joint sheet metal must overlap by at least 6 cm in the area of the joint, in the straight sections and also in the corner area.
To do so, the upper protective foil must be turned back in the area subsequently to be joined.
Overlap the VB joint sheet metal by at least 6 cm and press the two ends firmly together.
The joint must be glued over its full height and entire surface to prevent subsequent water permeation.
There must be no contamination on the adhesive surfaces that could interfere with bonding.
Secure the joint with one of the fixing clips provided and fold the protective foil back onto the special coating.
Prepared joints in the straight sections as well as the corner area.
Once the foundation slab has been concreted, and before the wall formwork is closed or the double wall elements have been set up, the remaining protective foil must be removed.
The concreting of the wall base and corresponding preparations must be carried out in accordance with the established technical standards.
Status: 23.03.2022
accessoires
accessoires appropriés
The joint sheet metal/joint tape connector establishes a reliable pressure water-tight connection between PVC joint tapes and coat...
Etriers de fixation pour couvre-joints métalliques pour couvre-joints métalliques revêtus et non revêtus à hauteur 160 mm ...
Contactez nous
We are happy to answer your questions